Buy land from the developer  (2) expand_more expand_less
Environmental impact assessment  (7) expand_more expand_less
Request for construction permit  (3) expand_more expand_less
Request for occupational permit  (3) expand_more expand_less
Application for EPZ user license  (3) expand_more expand_less

arrow_drop_up arrow_drop_down
chevron_right print

Preview & Print

Properties

Summary of the procedure

Institutions involved 5 expand_more expand_less

Prime Economic Zone Secretariat (x 2)
Prime Economic Zone Secretariat
Environmental Impact Assessment Experts
Environmental Impact Assessment Experts
National Bank of Rwanda
National Bank of Rwanda
Bank of Kigali
Bank of Kigali

Results 4 expand_more expand_less

EIA certificate (original, signed and with stamp)
EIA certificate (original, signed and with stamp)
Signed conditions of approval
Signed conditions of approval
Certificate of registration as an EPZ company
Certificate of registration as an EPZ company
EPZ developer / operator license
EPZ developer / operator license

Required Documents expand_more expand_less

Proof of identity (x 2)
Proof of identity
Online application
Online application
Project brief
Project brief
Panoramic view
Panoramic view
Perspective and site layout plans
Perspective and site layout plans
Land ownership
Land ownership
Location maps
Location maps
EIA study report
EIA study report
Deposit slip
Deposit slip
Payment receipt (BNR)
Payment receipt (BNR)
EIA certificate (original, signed and with stamp)
EIA certificate (original, signed and with stamp)
Application letter for construction permit
Application letter for construction permit
Project implementation plan
Project implementation plan
Environmental management plan.
Environmental management plan.
Deed plan
Deed plan
Project brief for construction permit
Project brief for construction permit
Two Perspectives vis a vis surroundings
Two Perspectives vis a vis surroundings
Topographic map
Topographic map
Architectural layout drawings
Architectural layout drawings
Water, plumbing and drainage drawings and details
 Water, plumbing and drainage drawings and details
General arrangement of artificial ventilation
General arrangement of artificial ventilation
Electrical, mechanical or fibre optical installation layout details
 Electrical, mechanical or fibre optical  installation layout details
Structural drawings, layout and details, including bar bending schedule and structural calculations
Structural drawings, layout and details, including bar bending schedule and structural calculations
Bills of quantity
Bills of quantity
Soil test results
Soil test results
Safety measure plan (Fire Management)
Safety measure plan (Fire Management)
Appointment
Appointment
Application letter
Application letter
Construction permit
Construction permit
Payment slip (BK)
Payment slip (BK)
Application letter
Application letter
Application form for EPZ user license
Application form for EPZ user license
Payment receipt
Payment receipt
Occupational permit
Occupational permit
Pre-feasibility study
Pre-feasibility study
Business plan
Business plan
Representatives
Power of attorney
Power of attorney
Proof of identity
Proof of identity

Cost detail

Estimate your cost

RWF 60,000
fee for construction permit
USD 2,500
application fee for EPZ license
USD 2,500
Application fee
  Min. Max.
Total time (sum): 3 d 26 d
of which:
Waiting time in queue (sum): 0mn 25mn
Attention at counter: 1h. 30mn 8h. 30mn
Waiting time until next step (sum): 3 d 25 d
General guidelines and procrdure for environment impact assessment General guidelines and procedure for environment impact assesment
  Article 2
Ministerial order No. 003/2008 of 15/08/2008 relating to the requirements and procedures for environ Ministerial order n°003/2008 of 15/08/2008 relating to the requirements and procedure for invironmental impact assessment
  articles 3, 4, 5, 7, 8, 9, 10, 11
Ministerial Order N°004 establishing the list of works, activities and projects that have to undertake  an environment impact assessment Ministerial Order N°004 establishing the list of works, activities and projects that have to undertake an environment impact assessment
  articles 2, 4 and annex
Organic law No. 04/2005 of08/04/2005 determining the modalities of protection, conservation and prom Organic law No. 04/2005 of 08/04/2005
  articles 67, 69, 70
The East african Community Customs Management Act The East african Community Customs Management Act Section 169 stipulates the specific requirements to obtain the EPZ operator status.
  Section tion 169