Investment incentives / Investment certificate

2
Submit application for investment certificate

Wait until next step

1 day  -  2 days

Contact details

Entity in charge

One Stop Centre Registration Portal


Tel: 1415 / +250 727 775 170
Email: onestop@rdb.rw, investorfeedback@rdb.rw
Website: http://osc.rdb.rw/en/

Expected results

1. Registration approval e-mail notification
Registration approval e-mail notification

Requirements

1. 01 - Libre deuda de patente
Application letter for investment certificate (original)
detailed content information on: http://osc.rdb.rw/ under the "investment certificate" section
2. 01 - Libre deuda de patente
Payment receipt (investment certificate) (Simple copy)
the reference number on the receipt should be entered where required and a scan copy of the receipt should be uploaded in the system
3. 01 - Libre deuda de patente
Certificate of domestic company registration (Simple copy)
For domestic companies
or 01 - Libre deuda de patente
Certificate of foreign company registration (Simple copy)
For foreign companies
or 01 - Libre deuda de patente
Certificate of enterprise registration (Simple copy)
For individual traders
4. 01 - Libre deuda de patente
Business plan (original)
5. EIA certificate (electronic copy)
EIA certificate (electronic copy) (Simple copy)
For projects that require environmental assessment
6.
Sector licence (Simple copy)
Licence granted by the relevant sector if applicable
7. Investment certificate checklist
Investment certificate checklist

Time frame

Waiting time until next step: Min.   1 day - Max.   2 days

Legal justification

1. Law n° 006/2021 of 05/02/2021 on investment promotion and facilitation
Law n° 006/2021 of 05/02/2021 on investment promotion and facilitation
Article 17-25

Additional information

The system automatically generates an email notifying the applicant that the application has been successfully submitted.
In case additional information is deemed necessary during the assessment process, the applicant will be notified by email.
When an application is rejected, the applicant is notified in writing of the reasons for rejecting the application within 2 working days from the date of receipt of the application.

Your investment business plan or feasibility study should clearly indicate following:
1. Executive summary of the project
2. Profile of the project promoter(s)
3. The project background
4. Market study or market analysis
5. Investment plan over five year period
6. The level of loan and equity financing
7. Projected statement of income and expenditure (5 years)
8. Projected balance sheet ( 5 years)
9. Projected statement of cash flows (5 years)
10. Payback period, NPV and IRR
11. Loan amortization schedule for the bank loan (if any)
12. Project implementation plan/ schedule)
13. Notes on assumption made in the business plan